Blog

Northstar Bluescope Steel Case Study

May 13, 2022 4:04:00 PM by: Excel Fluid Group



Messer - Bluescope - Pump Station 250x250Site:

Delta, OH

Middough with Messer 

North Star Bluescope Steel Lift Station

Application Overview:

We worked with Middough and Messer to design and build a pump station for North Star Bluescope Steel. This pump station is for collection of all surface water runoff and to transfer it off-site.

Pump Station Details:

We prefabricated a 5 ft. diameter by 15 ft. deep fiberglass wet well. This wet well structure has a 5 ft. diameter by 6 ft. deep valve vault. Barnes submersible non-clog pumps rated for 90 GPM @ 35 TDH were used and the entire station is being controlled by a Excel duplex control panel.

DOWNLOAD THE PDF

Installation:

The installation was completed by Messer with oversight from Excel Fluid Group as shown below.









Subscribe Here!

Submit a Project Inquiry