Site:
ODOT SR 64 Project 180408
Bowling Green, OH
Application Overview:
ODOT / City of Bowling Green worked with Poggemeyer Design Group and DLZ Inc. to convert the Two existing SR64/SR105 signalized ramp intersections at I-75 to single lane roundabouts, which included a new sanitary pump station adjacent to (BGSU) Bowling Green State University.
Pump Station Details:
Excel Fluid Group was contracted to supply and install the sanitary pump station per the project specifications which included the following: (1) 8’ x 30’ concrete wet well, (2) Flygt submersible pumps, (1) Easi-Set concrete controls building and all associated VFDs, control panels, flow-meter and air release valve.
Installation:
The installation was completed by Miller Bros. Construction Inc., Norwalk Concrete and Excel Fluid Group as shown below: