Blue Sky WRF Process Pump Station
Taylor, Texas
We worked with Kiewit and Sundt Construction to design and build a wastewater process pump station for the Blue Sky Water Reclamation Facility, located within the Samsung Semiconductor Facility in Taylor, Texas.
We prefabricated a 6-foot-diameter, 15-foot-deep fiberglass wet well equipped with two Sulzer 7.5 HP submersible non-clog pumps, each rated at 190 GPM at 50 TDH. The package included a duplex junction box for power terminations, while the control panel and instrumentation were provided under a separate contract. All discharge piping was 4-inch 316 stainless steel, complete with an integral bypass connection and an air release valve.
The installation was completed by Kiewit and the Sundt JV team with oversight from Excel Fluid Group as shown below: