Licking County Water / Wastewater worked with the Ohio Dept. of Transportation District 5 and 2LMN, Inc. Engineers to design a potable water booster pump station and new water main from Lakewood High School along U.S. 40 to the ODOT District 5 office. This system was designed to replace an existing underground fiberglass water tank located at the ODOT District 5 office.
The engineering team specified an Excel Fluid Group factory built booster station that included a fiberglass building with a mechanical / electrical room and a separate chemical feed room for a dosing pump and Sodium Hypochlorite day tank. A duplex vertical multistage pump skid with 10 Hp motors and variable frequency drive control panel was included to deliver up to 200 GPM per pump.
The installation was completed by ASK Services as shown below: